I

n 2022, as part of its move toward digital transformation, the Agricultural Bank of China (AgBank) began constructing a massive new data centre in the Horinger New Area of Hohhot, the provincial capital of the Inner Mongolia Autonomous Region. A key element in China’s strategy of channeling its computing resources from east to west, the finished New Area will serve as the country’s green computing powerhouse. The zone will house data centre built by several of China’s major bank, including AgBank, all of which will leverage the region’s rich natural resources and cool climate to achieve maximum energy efficiency and sustainability.

   Once complete, the new AgBank data centre will be one of the largest in China’s financial industry, with the capability to deliver data analysis and storage on a mammoth scale. From the outset, AgBank knew the project would necessitate not only a vast standby power system to ensure absolute energy continuity, but a dependable power solutions provider with the skills and experience to build it efficiently, reliably and to schedule.

   AgBank turned to Cummins China, headquartered in Beijing, to meet the challenge. The power company had the advanced power generation technologies—and the global reach and local support—needed to deliver. Cummins’ proven track record in supplying sustainable power solutions to mission-critical data centre was also instrumental in its securing the contract

   Cummins China was tasked with supplying standby power for the first phase of the new data centre, which covered a construction area of 209,000 sq m and included six computer room buildings, two warehouses, a support building, two substations, and four power buildings. The finished backup plant also had to align with the wider project quality objectives of meeting China’s construction, design and energy-efficiency standards, including its 3-Star Green Building Standard; and complying with the requirements for national standard Class A and Tier 4 computer rooms.

     Working with local Cummins distributors, Cummins China supplied and installed 74 high-voltage Cummins C2500D5A 10 kV 50 Hz diesel generator sets. This represents the largest number of units provided within any single project in China and, with an installed total capacity of 122.4 MW, the biggest single power volume supply in the country’s financial industry. Equipped with a heavy-duty engine, each C2500D5A generator set is a fully integrated power system designed for optimum performance, reliability and versatility in standby applications.

    The installation work saw the generator sets each housed in their own independent noise-reduction rooms located across all four (C1, C2, D1 and D2) 3-story power buildings. Six backup power supply systems employing an N+1 configuration were set up, with four systems of 12 paralleled generator sets in C1 and D1, and two systems of 13 paralleled generator sets in C2 and D2.

Posted 
Dec 14, 2025
 in 
Gensets
 category
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

More from 

Gensets

View All

Join Our Newsletter and Get the Latest
Posts to Your Inbox

No spam ever. Read our Privacy Policy
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.